March 2026 snapshotCommunity Support Programme
Government Transformation and Service Delivery
Record date: 31 March 2026
- Whole-life cost
- £1.0bn
- Published schedule
- 01/03/2023 – 09/03/2029
- NISTA delivery confidence
- Not disclosed
- Senior responsible owner
- Rachel Radice
What the project is for
Design, commission, procure and implement new rehabilitative services.
Departmental delivery commentary
The Delivery Confidence Assessment (DCA) rating at 25/26-Q4 is Amber. This is largely due to anticipated reduction in funding resulting in the potential for changes in project scope.
Schedule
The programme's end date at 25/26-Q4 is scheduled for 09/03/2029. The project is on track to deliver against the baseline schedule.
Cost
The programme's Whole Life Costs for 25/26-Q4 are £1,024.83m. The Whole Life Costs are based on the most recent business case and include optimism bias.
Benefits
The programme has not provided details of monetised benefits for financial year 25/26-Q4. This project currently reports no monetised benefits. The project benefits focus on the quality of services contracts.