MOJ
Current portfolio10K Additional Prison Places Estate Expansion Category D
Infrastructure and Construction
Record date: 31 March 2026
- Whole-life cost
- Not disclosed
- Published schedule
- 24/01/2020 – 20/03/2031
- NISTA delivery confidence
- RED
- Senior responsible owner
- Nigel Nuttall
What the project is for
The Category D Programme supports our 20,000 additional prison places commitment; it will provide additional permanent places across the Category D open prison estate
Departmental delivery commentary
Compared to financial year 24/25-Q4, the NISTA Delivery Confidence Assessment rating at 25/26-Q4 remains at Red. This is primarily due to issues arising from the administration of a key supplier.
Schedule
Compared to financial year 24/25-Q4, the project's end date at 25/26-Q4 changed from 20/09/29 to 20/03/31. This is primarily due to the programme’s key supplier entering administration and the resulting delays on delivery.
Cost
Exempt under Section 43 - Commercial interests
Benefits
This programme currently reports no monetised benefits. Due to the projected increasing prisons population, this programme focusses on increasing capacity and there are no monetised benefits to be claimed. The programme's other benefits are defined in the current baseline as: construction benefits and outcomes (capacity, modern methods of construction and sustainability); to enable an improvement in prisoner rehabilitation outcomes; and, during its construction, deliver local community benefits.