MOJ
March 2026 snapshotDecommission and Legacy Risk Migration (DLRM)
Information and Communications Technology (ICT)
Record date: 31 March 2026
- Whole-life cost
- £273.3m
- Published schedule
- 01/07/2021 – 30/09/2028
- NISTA delivery confidence
- Not disclosed
- Senior responsible owner
- John Laverick
What the project is for
The Decommissioning and Legacy Risk Mitigation (DLRM) Programme has been established to mitigate the risks presented by HMCTS legacy technology. The DLRM Programme will retire aged and unused applications and update and migrate existing applications to supported hosting environments
Departmental delivery commentary
Compared to financial year 24/25 Q4, the NISTA Delivery Confidence Assessment (DCA) rating at 25/26 Q4 remained at Amber. This is driven primarily due to continued delivery risk driven by complex design challenges.
Schedule
Compared to financial year 24/25-Q4, the programme's end-date at 25/26-Q4 changed from 31/03/28 to 30/09/28. This is primarily due to the programme allowing additional time to ensure a full closure process is completed.
Cost
Compared to financial year 24/25-Q4, the project's Whole Life Cost at 25/26-Q4 reduced to £273.28m. The Whole Life Cost remains aligned to the current baseline business case. All costs have been reported in 2024/25 base prices in line with NISTA requirements. This is a change from previous years where costs were reported in nominal prices. All costs reflect this accounting reduction regardless of any actual changes.
Benefits
The project's departmentally agreed Benefits at 25/26-Q4 (measured in £m) is 0. This project currently reports no monetised benefits. The project's benefits focus on reducing the risk of legacy technology through decommission, transition and replacement.