MOD
March 2026 snapshotBRIMSTONE 3
Military Capability
Record date: 31 March 2026
- Whole-life cost
- Not disclosed
- Published schedule
- 23/03/2017 – 31/01/2031
- NISTA delivery confidence
- Not disclosed
- Senior responsible owner
- Air Cdre Alun Roberts
What the project is for
Brimstone 3 (B3) sustains the precise, low-collateral air-to-surface Brimstone capability on the Typhoon platform, it is also being integrated onto the Protector platform.
Departmental delivery commentary
Compared to financial year 24/25 Q4, the NISTA/SRO Delivery Confidence Assessment (DCA) rating at 25/26 Q4 remained at Amber. This is primarily due to the following factors. 1. While awaiting formal endorsement of the revised programme baseline, it continues to manage resourcing constraints and finalisation of the operational safety case. 2. Key progress has been made, including continued stability of the schedule, safety case advancement and programme maturity.
Schedule
Compared to financial year 24/25-Q4, the programme's end-date at 25/26-Q4 remained the same at 31/12/2028.
Cost
Exempt under Section 43 - Commercial interests
Benefits
Compared to financial year 24/25-Q4, the project's departmentally agreed Benefits at 25/26-Q4 (measured in £m) remained at 0. This is primarily due to the following factors. No monetised benefits.