MOD
March 2026 snapshotASTUTE BOATS 1-7
Military Capability
Record date: 31 March 2026
- Whole-life cost
- £14.4bn
- Published schedule
- 17/03/1997 – Exempt under Section 24 - National security
- NISTA delivery confidence
- Not disclosed
- Senior responsible owner
- Saloni Sanghvi
What the project is for
To deliver the seven Boat Astute Class within approved performance, cost and time parameters, while actively contributing to the sustainment of the UK submarine design and manufacturing capability.
Departmental delivery commentary
Compared to financial year 24/25-Q4, the NISTA/SRO Delivery Confidence Assessment rating at 25/26-Q4 remained at Amber. This is primarily due to the following factors. 1. The Astute build programme has achieved the majority of its build and commissioning milestones in this financial year. However, the Delivery Confidence Assessment remains Amber because of potential delays in the in-water phase for Boat 6, and the build of Boat 7 based on current productivity rates.
Schedule
Exempt under Section 26 - Defence
Cost
Compared to financial year 24/25-Q4, the project's departmentally agreed Whole Life Cost at 25/26-Q4 (measured in £m) increased from £11,570.00 to £11,590.00. This is primarily due to a revised cost estimate for completion of the programme and inflation.
Benefits
Compared to financial year 2024/25-Q4, the project's departmental-agreed monetised benefits at 2025/26-Q4 remained at £0m.