DESNZ

Current portfolio

Project Seahorse

Government Transformation and Service Delivery

Official NISTA record

Record date: 31 March 2026

Whole-life cost
£276.7m
Published schedule
08/07/202431/12/2027
NISTA delivery confidence
RED
Senior responsible owner
Vicky Dawe

What the project is for

Project is to establish the Warm Homes Agency (WHA) – a dedicated public body to support the delivery of the Warm Homes Plan, and guide consumers through the transition.

Departmental delivery commentary

The SRO Delivery Confidence Assessment (DCA) rating at 2025/26 Q4 is Red. The project is operating within a changed organisational context and is undertaking replanning work to ensure that delivery plans remain realistic and achievable within available resources, while prioritising key activities such as the necessary Primary Legislation.

Schedule

The project joined the GMPP in 25/26. The expected project end date is currently 31/12/2027 but this is subject to replanning which is taking place over May to August 2026.

Cost

The Whole Life Costs figure (converted to real prices with base year 24/25) consists of resource costs for 25/26 to 28/29 and capital costs for 25/26 to 29/30, which are subject to funding. The resource costs are the costs to be incurred in establishing the agency, which includes set-up, implementation and transition costs. The capital portion of the whole life cost is made up of the capital required to transition existing IT systems over to the new agency, as well as creating new IT systems.

Benefits

The Warm Homes Agency is a key enabler of our Warm Homes Plan, designed to drive consumer demand for warmer, greener homes whilst galvanising the supply chain and coordinating delivery across the UK. By bringing together some schemes as well as advisory and assurance services currently split across DESNZ, Ofgem, and Salix, we are creating a clearer, more efficient system for households and taxpayers alike. As the scope is still being refined (subject to ministerial approval) full benefit quantification is not possible at this stage.