DSIT
Current portfolioProject Gigabit
Infrastructure and Construction
Record date: 31 March 2026
- Whole-life cost
- £5.2bn
- Published schedule
- 01/04/2021 – 31/12/2032
- NISTA delivery confidence
- Not disclosed
- Senior responsible owner
- Ben Whitestone
What the project is for
Project Gigabit provides gigabit-capable connectivity to homes and businesses that are not included in suppliers' commercial plans. The programme target is for next-generation gigabit broadband to be available nationwide by 2032.
Departmental delivery commentary
Compared to financial year 24/25 Q4, the NISTA/SRO Delivery Confidence Assessment (DCA) rating at 25/26 Q4 remained at AMBER. UK Gigabit coverage reached 90.76% in June 2026, according to ThinkBroadband. The programme is progressing largely to plan but there are some concerns over supplier access to finance and supply chain risks which may impact delivery.
Schedule
Compared to financial year 24/25-Q4, the project's end-date at 25/26-Q4 has been extended to 31/12/2032. This is to reflect a revised delivery timeline.
Cost
Compared to financial year 24/25-Q4 of £5,404m, the project’s departmentally agreed Whole Life Cost at 25/26-Q4 decreased to £4,831m. This is primarily due to the following factors, updated Open Market Review has fed into updated Central Delivery Forecast Model.
Benefits
The baseline benefits have remained at £5,434m (between Q4 2024/24 and Q4 2025/26) as the same return has been reported during this period.