HMLR
March 2026 snapshotLOCAL LAND CHARGES (LLC) PROGRAMME
Government Transformation and Service Delivery
Record date: 31 March 2026
- Whole-life cost
- £346.2m
- Published schedule
- 01/03/2014 – 29/12/2028
- NISTA delivery confidence
- Not disclosed
- Senior responsible owner
- Iain Banfield
What the project is for
The Local Land Charges (LLC) Programme is transforming a fragmented, inefficient service currently delivered by local authorities (LAs) to a single national, digital register across England and Wales. LLCs are generally restrictions or prohibitions on the use of land, such as planning consents or tree preservation order, which binds successive owners and occupiers. This information is obtained as part of LA searches completed in the property buying process and is integral to the purchasers’ investment decision.
Departmental delivery commentary
Compared to financial year 24/25 Q4, the SRO Delivery Confidence Assessment (DCA) rating at 25/26 Q4 remained at Amber. This is primarily due to the need for proven end to end delivery at scale by external suppliers, which will be proven in 2026, and external dependencies the programme manage on a case by case basis.
Schedule
Compared to financial year 24/25-Q4, the project's end-date at 25/26-Q4 increased from 31/03/2027 to 29/12/2028. This is primarily due to a better understanding of delivery length assumptions, and completion of detailed programme delivery planning. This remains in line with the refreshed LLC Full Business Case.
Cost
Compared to financial year 24/25-Q4, the project's departmentally agreed Whole Life Cost at 25/26-Q4 remained the same. Following HMT FBC approval, revised baselines will be forecasted.
Benefits
No changes to agreed benefit baselines until programme Monitoring & Evaluation Phase 3 completes in 2027. Current benefit realisation on track.